Project Update for Friday, July 29, 2022 Contractors continue make ready construction out of the Baskin substation and north of the Log Cabin substation. Make ready construction consists of clearing brush and trees growing into the lines, setting taller poles and/or...
Fiber, fiber everywhere! Fiber, fiber everywhere! Crews are actively hanging fiber in the Baskin area and readying the internet network for broadband service to all NELPCO members. If you live in the Baskin area (or Liddieville, Fort Necessity, Crowville or Mangham)...
Project Update for Friday, July 15, 2022 Our Volt Broadband Fiber To The Home project has reached several milestones. First, the fiber is hung and all road crossing for mainline fiber have been completed. Splicing will begin Monday, July 18th and testing will begin to...